Bipartisan Infrastructure Law (BIL)
The Bipartisan Infrastructure Law (BIL), also known as the Infrastructure Investment and Jobs Act (IIJA) (Public Law 117-58), provides a $17.1 billion investment for Civil Works Projects that address water resources and infrastructure needs for the nation. The IIJA provides $4,000,000,000 to remain available until expended, in Operation and Maintenance (O&M) funding ($2,000,000,000 in FY22, $1,000,000,000 in FY23, and $1,000,000,000 in FY24).
HQ BIL Site
OPORD 2023-25 (Bipartisan Infrastructure Law - Project Signage Requirements) - 11 April 2023
Annex A - BIL Master Project List
Annex B - WH33 Project List
Annex C - Investing in America Brand Guide
Annex D - 2023-02-23 Controller Alert Enhancing Transparency Bipartisan Infrastructure Law
Typical Installation image
Standard Sign (ai)
Standard Sign (eps)
Standard Sign (pdf)
Corps Construction Identification Sign
Safety Sign (ai)
Standard Sign (eps)
Standard Sign (pdf)
Corps Construction Safety Sign
Safety Sign (ai)
Standard Sign (eps)
Standard Sign (pdf)
Download Corps Helvetica Fonts
Reporting BIL Signage
- Instructions for BIL Signage Requirements:
- This PDF includes step by step instructions and requirements for adding milestones to project schedules and uploading of signage images to CMI.
- Milestone: Every project receiving BIL funding is required to enter milestone CW444 in the project schedule for signage. CW444 will be reflected in the current PROMIS/P2 schedule and is not a reason to rebaseline.
- Images: Once signs are placed at the project site, every project is required to upload pictures associated with the schedule milestone into the CMI System through the PROMIS Portal.
- The ability to upload images into CMI will be available the week of 12 June. A follow up email will be sent by the HQ Supplemental Programs Branch (SPB) once this feature is available. We are disseminating the instructions now, to allow the field time to begin adding the CW444 milestone to the project schedule.
- For additional information and requirements of BIL Signage, please review OPORD 2023-25
- Suspense for adding CW444 milestones to project schedules is Friday, 30 Jun 2023. HQ SPB will begin checking the milestone date the week of 3 July 2023. This requirement is to support the quarterly data call to ASA (CW) on 12 July 2023.
- Please share with others as appropriate to ensure widest dissemination. If you have any questions on this requirement my point of contact for this effort is the HQ Supplemental Programs Branch, which can be reached at: DLL-HQ-CECW-EMERGENCYSUPP-HQ-TEAM@usace.army.mil.
|